صفحه اصلی Administrative & Technical Capabilities How to install and test and commissioning of power transformers and distribution

How to install and test and commissioning of power transformers and distribution

One of Other features of the professional company can be installing, testing and commissioning of power transformers and distribution together with the respective bus duct noted with interest that the company experienced phallic force and experienced executive who's aware of all stages Installation of power and distribution transformers are acting and eventually to do all tests defined for power transformers and distribution and ultimately test the differential stability and trans ref according to the following items shall act:

LOL: Low oil level
49oil: oil temperature indicator with alarm & trip
49W: winding temperature indicator with alarm & trip
63: Pressure relief vent with alarm & trip
96: Buchholz relay with alarm & trip
87: Differential protection relay
64: Restricted earth fault relay
CT: Current transformer

That including the company's test equipment can be items mentioned below:

1. Tree phase secondary injection test unit
2. Primary injection test unit 2000
3. High voltage insulation test apparatus (35KV)
4. Oil treatment
5. Digital multi meter

 

 

Language Selection

Persian (Iran Islamic)English (United Kingdom)